Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 01/05/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1-5-26: reinforcement on cmu walls verified per plans-3rd lift for electrical building approved at 14'. |
| 01/14/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1-14-26: reinforcement/anchor bolts verified per plans-okay to grout 4th lift at 15' 8". |
| 01/22/2026 |
COT - HCBU - Masonry Pregrout |
|
Passed |
CMU walls topped out at 15’ - 18’; grouted |
| 07/10/2025 |
COT - HCBU - Masonry Pregrout |
|
Canceled |
|
| 12/10/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Partial pass. 1st lift at electrical building approved. Okay to grout. 12/10/2025 |
| 12/18/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
12-18-25: reinforcement at cmu walls of electrical building verified per plans-okay to grout 2nd lift at 8'. |