Inspection Status: Partial Pass
Inspection History: COT - HCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 01/09/2025 |
COT - HCPL - Sewer |
|
Partial Pass |
see DP permit for site sewer |
| 03/10/2025 |
COT - HCPL - Sewer |
|
Partial Pass |
|
| 03/17/2026 |
COT - HCPL - Sewer |
|
Passed |
|
| 03/20/2025 |
COT - HCPL - Sewer |
|
Partial Pass |
East portion of Staff Living Building: 4” waste line with 3” lateral lines (4 each) intersections. Ok to,cover progress areas. |
| 03/24/2025 |
COT - HCPL - Sewer |
|
Partial Pass |
Sewer line (4”) approximately 55’ is Ok to cover . Laterals at GL: G/1-2 do not have enough coverage, need to be lowered (less than 4” coverage) |
| 03/28/2025 |
COT - HCPL - Sewer |
|
Partial Pass |
3-28-25, underground plumbing/sewer on east section of staff living verified per plans. Okay to backfill approximately 70' of 4" sewer together with progress areas related to DWV. Shading required. |