Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/07/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor has not installed. The dugout outside will be installed at another time. |
| 02/24/2025 |
ENGR Engineering Final
|
|
Passed |
|
| 05/24/2024 |
ENGR Engineering Final
|
|
Not Ready |
will remove extra DP inspections per conversation. |
| 09/30/2024 |
ENGR Engineering Final
|
|
Partial Pass |
Call character to install two number four bars in the front sells of the trash enclosure |