Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2025 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | DWV and domestic water lines on test. Mop sink south wing. And rooms 147-148. Okay to proceed progress areas. 6/16/2025 | |
| 07/10/2025 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | DWV and domestic water lines on test. Mop sink south wing. And rooms 147-148. Okay to proceed progress areas. 6/16/2025 7/10/25: gas pressure test and domestic water pressure test approved. Ok to insulate water lines |
|
| 10/24/2025 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 10-24-25: all DWV/Domestic properly supported and verified under test. Remainder of plumbing will be verified after extractor is installed. | |
| 10/30/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | Ok to set ceiling tiles. |