Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/25/2025 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
4/25/25: Smoke test at hood duct approved ok to proceed. |
| 10/24/2025 |
COT - HCME - Mechanical Progress |
|
Partial Pass |
10-24-25: correct tears on HVAC wrap throughout, seal penetrations at turnout room, label all fire/electrical junction boxes above ceiling, hood requires 2 layers of fire wrap. |
| 12/03/2025 |
COT - HCME - Mechanical Progress |
|
Passed |
12-3-25: approved. |