Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 01/09/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
1/9/24: hard duct in corridor 131 per plan ok to proceed with insulation. |
| 02/26/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
Duct system throughout structure, ensure system is appropriately insulated. |
| 05/15/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
5-15-25, mechanical above ceiling verified per plans along secured staff entry to kitchen areas- okay to proceed with construction at progress locations. |
| 10/24/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
10-24-25: correct tears on HVAC wrap throughout, seal penetrations at turnout room, label all fire/electrical junction boxes above ceiling, hood requires 2 layers of fire wrap. Mechanical/plumbing at rooftop will be inspected at finals. |
| 10/30/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Passed |
Ok to set ceiling tiles |