Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
Permit Number - TC-COM-0123-00490
Inspection Description - COT - HCBU - Preslab
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/24/2024 | COT - HCBU - Preslab | Partial Pass | 6/28/24: reinforcement per plan at exterior footings (Dorm Rooms, Day Room, Electric, Lobby, Training(excluding N. Wall), Secured Patio, Captains Office, kitchen, pantry, EMS, Staff patio) 7/3/24: phase 2 reinforcement at footings around exterior perimeter at rooms (144,143,145,146,147 and 149), footing type WF1 and WF2. 7/24/24: phase 3 reinforcement at footings per plan ok to proceed with concrete pour. |
|
09/19/2024 | COT - HCBU - Preslab | Partial Pass | 9/19/2024: first pour north wing phase 1. Okay for concrete placement. | |
10/01/2024 | COT - HCBU - Preslab | Partial Pass | South wing. ( 144,143,145,146,147,148,149) okay for concrete placement. 10/1/2024 |