Permit: TC-COM-0123-00490

Parcel: 13701005H


Addresses:

5500 S NOGALES HY

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
10/28/2024 COT - HCBU - Masonry Pregrout  Partial Pass Reinforcing steel, horizontal and vertical rebar for north wing cmu walls. N, S, and W walls of dorms, N, S, and W walls of day room, S wall of gym, N walls of public lobby, N, E, and S walls of training room, N, E, and W walls of captain's office; all from 0-4'8". N, E, and W walls of gym from 0-3'5". Okay to grout 1st lift. 10/28/2024
11/18/2024 COT - HCBU - Masonry Pregrout  Partial Pass Reinforcing steel, horizontal and vertical rebar for north wing cmu walls. N, S, and W walls of dorms, N, S, and W walls of day room, S wall of gym, N walls of public lobby, N, E, and S walls of training room, N, E, and W walls of captain's office; all from 0-4'8". N, E, and W walls of gym from 0-3'5". Okay to grout 1st lift. 10/28/2024
11/18/24: vertical and horizontal rebar and reinforcement at dorms South,East and West walls per plan at 2nd lift from 4'8"-9'4" . Pending North wall at dorms.
11/22/2024 COT - HCBU - Masonry Pregrout  Partial Pass Reinforcing steel, horizontal and vertical rebar for north wing cmu walls. N, S, and W walls of dorms, N, S, and W walls of day room, S wall of gym, N walls of public lobby, N, E, and S walls of training room, N, E, and W walls of captain's office; all from 0-4'8". N, E, and W walls of gym from 0-3'5". Okay to grout 1st lift. 10/28/2024
11/18/24: vertical and horizontal rebar and reinforcement at dorms South,East and West walls per plan at 2nd lift from 4'8"-9'4" . Pending North wall at dorms.
11/22/24: vertical and horizontal rebar reinforcement at Dorms South and West wall at 15'4" per plan ok to proceed.
12/03/2025 COT - HCBU - Masonry Pregrout  Passed 12-3-25: previously inspected & approved.
12/04/2024 COT - HCBU - Masonry Pregrout  Partial Pass Reinforcing steel, horizontal and vertical rebar for north wing cmu walls. N, S, and W walls of dorms, N, S, and W walls of day room, S wall of gym, N walls of public lobby, N, E, and S walls of training room, N, E, and W walls of captain's office; all from 0-4'8". N, E, and W walls of gym from 0-3'5". Okay to grout 1st lift. 10/28/2024
11/18/24: vertical and horizontal rebar and reinforcement at dorms South,East and West walls per plan at 2nd lift from 4'8"-9'4" . Pending North wall at dorms.
11/22/24: vertical and horizontal rebar reinforcement at Dorms South and West wall at 15'4" per plan ok to proceed.
12/09/2024 COT - HCBU - Masonry Pregrout  Partial Pass Reinforcing steel, horizontal and vertical rebar for north wing cmu walls. N, S, and W walls of dorms, N, S, and W walls of day room, S wall of gym, N walls of public lobby, N, E, and S walls of training room, N, E, and W walls of captain's office; all from 0-4'8". N, E, and W walls of gym from 0-3'5". Okay to grout 1st lift. 10/28/2024
11/18/24: vertical and horizontal rebar and reinforcement at dorms South,East and West walls per plan at 2nd lift from 4'8"-9'4" . Pending North wall at dorms.
11/22/24: vertical and horizontal rebar reinforcement at Dorms South and West wall at 15'4" per plan ok to proceed.
12/9/24: first lift at rooms 144,143,145,146,148 ok to proceed with grout at listed area. 3rd lift at 109,112,114,119,118,110.