Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
Permit Number - TC-COM-0123-00490
Inspection Description - COT - HCPL - Plumbing Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2025 | COT - HCPL - Plumbing Progress | Partial Pass | ||
| 04/02/2025 | COT - HCPL - Plumbing Progress | Partial Pass | 4-2-25, in wall DWV verified under test on dorm room bathrooms,laundry room, north wall of dining room, kitchen prep area, ADA public restroom, training room , north wall of firefighter office. Okay to continue with construction at progress areas | |
| 06/13/2025 | COT - HCPL - Plumbing Progress | Partial Pass | 6/13/2025 Pressure test on domestic water meter to building and sanitation water test to street from previously inspected areas. Okay to backfill progress areas. Shading required. | |
| 08/20/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required | |
| 08/21/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. |
|
| 09/06/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. |
|
| 09/10/2024 | COT - HCPL - Plumbing Progress | Partial Pass | Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 | |
| 10/24/2025 | COT - HCPL - Plumbing Progress | Passed | 10-24-25: approved. | |
| 11/15/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. |
|
| 11/22/2024 | COT - HCPL - Plumbing Progress | Not Ready | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. 11/21/24: not ready |
|
| 12/02/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. 11/21/24: not ready 12/2/24: inspection of sanitary to cover on south east corner partial pass for 3" under test. |
|
| 12/09/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. 11/21/24: not ready 12/2/24: inspection of sanitary to cover on south east corner partial pass for 3" under test. 12/9/24: sand/oil interceptor under pressure ok to backfill. |