Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
Permit Number - TC-COM-0123-00490
Inspection Description - COT - HCPL - Plumbing Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/20/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required | |
08/21/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. |
|
09/06/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. |
|
09/10/2024 | COT - HCPL - Plumbing Progress | Partial Pass | Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 | |
11/15/2024 | COT - HCPL - Plumbing Progress | Partial Pass | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. |
|
11/22/2024 | COT - HCPL - Plumbing Progress | Not Ready | 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required. 8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill. 9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required. Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024 11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section. 11/21/24: not ready |