Permit: TC-COM-0123-00490

Parcel: 13701005H


Addresses:

5500 S NOGALES HY

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
03/07/2025 COT - HCPL - Plumbing Progress  Partial Pass
04/02/2025 COT - HCPL - Plumbing Progress  Partial Pass 4-2-25, in wall DWV verified under test on dorm room bathrooms,laundry room, north wall of dining room, kitchen prep area, ADA public restroom, training room , north wall of firefighter office. Okay to continue with construction at progress areas
06/13/2025 COT - HCPL - Plumbing Progress  Partial Pass 6/13/2025 Pressure test on domestic water meter to building and sanitation water test to street from previously inspected areas. Okay to backfill progress areas. Shading required.
08/20/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required
08/21/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
09/06/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required.
09/10/2024 COT - HCPL - Plumbing Progress  Partial Pass Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024
10/24/2025 COT - HCPL - Plumbing Progress  Passed 10-24-25: approved.
11/15/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required.

Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024
11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section.
11/22/2024 COT - HCPL - Plumbing Progress  Not Ready 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required.

Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024
11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section.
11/21/24: not ready
12/02/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required.

Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024
11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section.
11/21/24: not ready
12/2/24: inspection of sanitary to cover on south east corner partial pass for 3" under test.
12/09/2024 COT - HCPL - Plumbing Progress  Partial Pass 8/20/24: North half of building Plumbing underground per plans. Pending corrections at laundry room and missing Clean out at dining room. Ok to backfill approved areas. Shading required.
8/21/24: North half of building plumbing underground per plans. Corrections were made . Ok to backfill.
9/6/24: plumbing Underground at Apparatus Bay per plans ok to backfill. Shading required.

Turnout room, decon shower , workshop. Approved. Okay to backfill progress areas. Shading required. 9/10/2024
11/15/24: county inspection at tap passed ok to cover the first 60 feet. Passed test at first section.
11/21/24: not ready
12/2/24: inspection of sanitary to cover on south east corner partial pass for 3" under test.
12/9/24: sand/oil interceptor under pressure ok to backfill.