Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 11/18/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
11-18-24, verified electrical underground for island #1. Verified as per approved plans, depth/placement of conduits and length of 1500 feet. Okay to backfill trench with shading. Contractor will schedule underground electrical for islands 2 and 3 at later date. |
| 11/21/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
11-21-24, conduit in place for second island. Verified as per approved plans. Okay to backfill. |
| 11/26/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
11/26/2024 conduit in place for third island. Per approved plans. Electrical room x6 3"conduit stubbed up to pole box 15. From pole box 15 heading north approximately 45´to future pole box. Station 691. Okay to backfill progress areas. |
| 11/27/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
11-27-24, total of 19 light cages inspected. Reinforcement/depth on 18 were verified as per approved plans. However, light cage on the far west end of island 2 does not meet depth requirements. Okay to proceed on the remaining 18 but a reinspection is required light cage in question. |
| 12/03/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
12-3-24, reinspection of light cage on island 2 is approved. Okay to continue with construction. |
| 12/04/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
12-4-24, all light cages verified as per approved plans. Okay to pour concrete. |
| 12/31/2024 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
12-31-24, verified schedule 40 conduits for island's 1, 2, 3 leading to panels/ct near main entrance. Okay to backfill and continue with construction. |