Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
Permit Number - TC-COM-0123-00459
Inspection Description - COT - HCEL - Electrical Underground
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/18/2024 | COT - HCEL - Electrical Underground | Partial Pass | 11-18-24, verified electrical underground for island #1. Verified as per approved plans, depth/placement of conduits and length of 1500 feet. Okay to backfill trench with shading. Contractor will schedule underground electrical for islands 2 and 3 at later date. | |
11/21/2024 | COT - HCEL - Electrical Underground | Partial Pass | 11-21-24, conduit in place for second island. Verified as per approved plans. Okay to backfill. |