Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
11/18/2024 COT - HCEL - Electrical Underground  Partial Pass 11-18-24, verified electrical underground for island #1. Verified as per approved plans, depth/placement of conduits and length of 1500 feet. Okay to backfill trench with shading. Contractor will schedule underground electrical for islands 2 and 3 at later date.
11/21/2024 COT - HCEL - Electrical Underground  Partial Pass 11-21-24, conduit in place for second island. Verified as per approved plans. Okay to backfill.
11/26/2024 COT - HCEL - Electrical Underground  Partial Pass 11/26/2024 conduit in place for third island. Per approved plans. Electrical room x6 3"conduit stubbed up to pole box 15. From pole box 15 heading north approximately 45´to future pole box. Station 691. Okay to backfill progress areas.
11/27/2024 COT - HCEL - Electrical Underground  Partial Pass 11-27-24, total of 19 light cages inspected. Reinforcement/depth on 18 were verified as per approved plans. However, light cage on the far west end of island 2 does not meet depth requirements. Okay to proceed on the remaining 18 but a reinspection is required light cage in question.
12/03/2024 COT - HCEL - Electrical Underground  Partial Pass 12-3-24, reinspection of light cage on island 2 is approved. Okay to continue with construction.
12/04/2024 COT - HCEL - Electrical Underground  Partial Pass 12-4-24, all light cages verified as per approved plans. Okay to pour concrete.
12/31/2024 COT - HCEL - Electrical Underground  Partial Pass 12-31-24, verified schedule 40 conduits for island's 1, 2, 3 leading to panels/ct near main entrance. Okay to backfill and continue with construction.