Inspection Status: Correction Required
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/09/2000 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. SOIL WATER TEST OK 2. OK TO BACKFILL TRENCH |
| 02/08/2000 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. FLAT VENTING FOR WATER CLOSET IN RM 120 NOT TO CODE CAN NOT USE WET VENT FROM VERTICAL TO HORIZONTAL DRAINAGE 2. RE TEST SYSTEM 3. WILL REQUIRE REVISED AND APPROVED DRAWING ON PLDG IZO BEFORE FINAL 4. ALL CORRECTIONS HAVE BEEN MADE 5. OK TO BACKFILL TRENCH |
| 02/08/2000 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/08/2000 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0000* |
| 02/07/2000 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. SOIL WATER TEST WAS DOWN DUE TO FITTING THAT WAS NOT GLUED @ WATER CLOSET @ WEST SIDE OF BLDG 2. WATER CLOSET IN UNIT 120 ROUJGH PLDG NOT TO PLAN MUST BE CONVENTIONAL ROUDGH NOT FLAT VENTED 3. REMOVE BACKWATER VALVE (NOT REQUIRED) AND REVERSE COMBOS FOR C.O. 4. RETEST SYSTEM 5. NOTE: WATER CLOSETS ARE 4 ALL THE WAY ON PLAN. |
| 02/07/2000 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0000* |