Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 01/08/2002 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 03/08/2001 |
FRAMING |
|
Partial Approval |
IVRS - Inspection 0000*/1. GAS LINE NOT ALLOWED UNDER CONCRETE SLAB UNDER COVER. 2. WINDOW FORM GARAGE TO HOUSE MUST BE FIRE RATED OR BLOCKED IN. OK TO DRY IN ROOF AND EXTERIOR. |
| 01/24/2001 |
FRAMING |
|
Denied |
IVRS - Inspection 0950*/1. POST CAPS MUST BE 4, LCE-4 CLIPS OR 2, AC 4 CLIPS. 2. POST REQUIRED UNDER WEST END OF DOULBE PAR LAM (4 X 4) 3. H2.5 CLIPS REQ. 1 1/4" TICO NAILS. ROOF SHEATHING MIN 1/2" O.S.B. NAILED W/8D AT 6" O.C. ENDS AND EDGES 12" FIELD. NOTE: POST FOOTINGS OK. |
| 06/09/2000 |
FRAMING |
|
Denied |
IVRS - Inspection 0925*/1. SPLICED BEAMS NOT ALLOWED. 2. EXPOSE FOOTER ON WEST WALL TO 12" BELOW GRADE. 3. NORTH WALL CANNOT BE CONSTRUCTED OF SPLICED STUDS. BEARING STUDS MUST BE FULL LENGTH. REPLACE 9 STUDS. 4. NO PLANS, OR PERMIT ON SITE NO ANSWER AT DOOR. |