Permit: T99CM02881

Parcel: 140440740

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
06/02/2008 FRAMING Approved IVRS - Inspection :*
03/26/2008 FRAMING Partial Approval IVRS - Inspection :*
08/27/1999 FRAMING Correction Required ADDTL COMMS - 1. I NEED TO TALK WITH, OR MEET WITH PERSON DOIN THE WORK. SOME PROBLEMS 2. PLEASE BRACE THE BUILDING AND INSTALL H2-5 TO WALLS, I NOTED IT ON YOUR PLAN SEE 3RD PAGE 3. BRACING USING FLAT STRAPING MUST X BRACE BOTTOM TO TOP PLATE AT ANGLES OF NOJ MORE THAN 60 DEGREE OR LESS THAN 45 DGR 4. I LEFT A SIMPSON CATALOG, FOR YOU TO USE SEE BRACING
08/27/1999 FRAMING Denied IVRS - Inspection 0999*
07/28/1999 FRAMING Correction Required ADDTL COMMS - 1. INSTALL ROOF SHEATHING. 2. TEMPORARY BRACING ON WALLS 3. BOTTOM PLATES WERE TOO BE OF TREATED LUMBER, YOU NEED ZINC CHROMATE, OR A WOOD PRESERVATIVE. 4. YOU NEED TO INSTALL HARDWARE, H2.5 STUD TO PLATES, AT TOP PLATE, YOU NEED SOMETHING TO TIE 4 PLATES TO STUD TO RAFTER. 5. YOU NEED MINIMUM 3 STUDS AT EACH CORNER. 6. PLAN CALLS FOR 3(2X12) FOR HEADER?
07/28/1999 FRAMING Not ready for Inspection NOT READY FOR INSPECTION