Permit: T99CM02118

Parcel: 137276450


Addresses:

1650 W VALENCIA RD


Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Permit Number - T99CM02118

Inspection Description - PLUMBING - ROUGH, SOIL

Inspection Status - Approved

Date Description Inspector Results Comments
10/19/2000 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection 0000*
GROCERY AREA BATHROOMS ALL CORRECTIONS MADE FINAL OK
MOP SINK IN STORAGE OK
FRONT BATHROOMS OK ALL CORRECTIONS MADE
SHAMPOO BOWLS OK OK FOR C OF O PENDING ANY OTHER INSPECTIONS
10/12/2000 PLUMBING - ROUGH, SOIL Not ready for Inspection NO ONE IN OFFICE
I WALKED THROUGH THE JOBSITE AND WAS UNABLE TO LOCATE ANYONE
CALL BACK IN FOR TOMORROW
10/09/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
ENTRY WAL JANITORS CLOSET FINAL OK
ALL THREE COMP SINKS AND HAND SINKS IN KITCHEN'S OK FINAL
ALL OTHER FIXTURES IN KITCHENS OK FINAL
10/02/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
FLORAL INTERMEDIATE OK
OK TO COVER
BREAKROOM INTERMEDIATE OK
OK TO COVER
PHOTO LAB TRIM OK PLEASE EXTEND C.O. TO FINISH WALL
ADDITIONAL SINK ROUGH IN HAIR CARE OK
COMPRESSED AIR IN AUTO (TLE) OK
FINAL GAS CONNECTIONS IN TLE OK
SOUTH MAIN BATHROOMS NOW COMPLETE
09/27/2000 PLUMBING - ROUGH, SOIL Partial Approval FRONT BATHROOMS FINAL
WOMEN'S BATHROOM HC WATER CLOSET MIN 18" SIDEWALL
SMOKING LOUNGE NOTED DEMO AND FUTURE PLANS
AUTO CENTER BATHROOM INTERMEDIATE
WATER PRESSURE TEST OK TO ISOLATION VALVE
DWV OK
CLOSET FLAGE OK
OK TO COVER WALLS FLORAL INTERMEDIATE
DWV OK
WATER PRESSURE TEST OK
OK TO COVER WALLS
09/21/2000 PLUMBING - ROUGH, SOIL Partial Approval TRAINING, TLE (TIRE LUBE EXPANIONS)
ROUGH ELECTRICAL
TRAINNING AREA, TIRE LUBE EXPRESS AREA ROUGH ELECTRICAL APPROVED
09/15/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
09/14/2000 PLUMBING - ROUGH, SOIL Partial Approval 1. FLORAL AREA UNDERGROUND OK
2. TIE IN TO EXISTING OK
3. OK TO COVER
4. WATER TEST OK
09/10/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
09/07/2000 PLUMBING - ROUGH, SOIL Partial Approval OK TO HOOK UP TRENCH DRAINS
INTERCEPTOR AND SEWER TIE IN OK
WATER TEST OK
OK TO COVER
09/05/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
AUTO CENTER DWV OK
OK TO HOOK UP TRENCH DRAINS
TESTED TO JUST INSIDE LUBE PIT
NEED TO SEE INTERCEPTOR AND TEST
08/29/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
08/28/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
08/25/2000 PLUMBING - ROUGH, SOIL Partial Approval 1. PHOTO LAB WASTE AND VENT OK
WATER TEST TO 42" OK
TIE IN OK
OK TO COVER
08/22/2000 PLUMBING - ROUGH, SOIL Partial Approval 444-7504 MIKE
RET WALL RISER OK
WATER TEST OK
OK TO COVER
NEED TO SEE COMPLETED VENT
08/12/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
SOIL WATER TEST OK
P.O.C. OF NEW BLDG DRAIN TO EXSISTING BLDG DRAIN OK
OK TO BACKFILL TRENCH
NOTE: THIS INSPECTION IS FOR FLOOR SINK IN FLOWER SHOP ONLY
08/03/2000 PLUMBING - ROUGH, SOIL Partial Approval UNDERGROUND AT HAIRCARE OK WATER TEST OK
INTERMEDIATE AT PHARMACY OK
WASTE AND VENT OK
WATER OK
07/24/2000 PLUMBING - ROUGH, SOIL Partial Approval 1. PHARMACY ROUGH SOIL OK WATER TEST OK
2. SS TO HAIR CARE 4" UNDERGROUND OK
3. DAIRY COOLER REVISED DRAWING OK WATER TEST OK OK TO BACKFILL
07/20/2000 PLUMBING - ROUGH, SOIL Partial Approval 1. TLE UNDERGROUND OK TOILET ROOM AND 4" BUILDING DRAIN
2. VESTIBULE AREA JANITOR CLOSET OK OK TO COVER 4"
3. REPLACE SAN CROSSES W/APPROVED FITTINGS IN BATHROOM AT VERTIBALE AREA
07/11/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
1. SOIL WATER TEST OK
2. P.O.C. OF NEW BLDG SEWER TO EXSISTING BLDG SEWER OK
3. THIS INSPECTION IF FOR 4" BLDG DRAIN AT FUTURE BANK AND COURTESY DESK
4. OK TO BACKFILL TRENCH
05/03/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK 2 OUTSIDE INTGR (WEST SIDE) NEED AS BUILT ON S.W. G. CORNER
05/03/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
05/01/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK COL J. NORTH TO SEWER CONNECTION AND 2-LINES TO DAIRY SECTION.
05/01/2000 PLUMBING - ROUGH, SOIL Partial Approval PARTIAL APPROVAL
04/26/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - PARTIAL C.W. AND VENT CUL G-9 TO J-8
04/26/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
04/20/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK WASTE ON WASTE SIDE AND TEST UP TO 2 WAY C.O. OK REVENTS TEST ON MAC DONALDS VISION CENTER VTR 03035-PARTIAL
04/20/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
04/19/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - 1. APPROVE G. WASTE COL D&E. C.W. AND VENTS COMPLETE 2. DISCHARGE FROM INTER TO MAIN LINE 3. OK WATER COPPER TEST @ MAC DONALDS AND VISION CENT NOTE: QUESTION ON GREASE INTER ON DISTANCE OF FIXTURES AND CONNECTED TO C. WASTE AND VENT SYSTEM AS PER PLAN
04/19/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
04/10/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/31/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - COL E-G SOUTH TO WEST WALL WASTE AND VENT SYSTEM.
03/31/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/28/2000 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
03/24/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK D-6 -COL 3 TO D-9 D-6 COLS
03/24/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/23/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK COL LINE #3 COL LINE D-6 TO E-9 AND COL LINE #4
03/23/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/21/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/17/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - OK 3 FLOOR SINK WILL NEED AS BUILTS ON VENT WEST END (MAC DONALD)
03/17/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/16/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/15/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - COL LINE 2 THRU 4 LINE J THRU A SUBJECT TO VENT @ FD WEST END
03/15/2000 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
03/10/2000 PLUMBING - ROUGH, SOIL Correction Required ADDTL COMMS - REJECTED- SPEC FOR PLBG MATERIAL C.I. OR PVC ABS INSTALL
03/10/2000 PLUMBING - ROUGH, SOIL Denied DENIED