Inspection Status: Approved
Inspection History: STUCCO MESH
| Date |
Description |
Inspector |
Results |
Comments |
| 07/23/2001 |
STUCCO MESH |
|
Approved |
IVRS - Inspection 0000* |
| 06/07/2000 |
STUCCO MESH |
|
Correction Required |
ADDTL COMMS - MAIN BLDG ONLY,NOT CARPORT AREA |
| 06/07/2000 |
STUCCO MESH |
|
Partial Approval |
IVRS - Inspection 0000* |
| 06/02/2000 |
STUCCO MESH |
|
Not ready for Inspection |
IVRS - Inspection 0000*1. THE EXTERIOR FOAM AND LATH DOES NOT COMPLY WITH UBC THREE COAT SYSTEM NOR TWO COAT SYSTEMS. 2. A 2 LAYER SUBSTRATE OF 15# CONTRUCTION PAGER OVER THE OSB MAY ALSO BE REQUIRED. PLEASE CONTACT OR VISIT WITH PLANS REVIEW TECH. REYES ARVAYO CONCERNING THIS PHASE OF CONTRUCTION. |
| 05/24/2000 |
STUCCO MESH |
|
Not ready for Inspection |
NOT READY FOR INSPECTION/1. NEED I. C. B. O. REPORT FOR THE TYPE 1 COAT SYS. YOU ARE USING, FOR PROPER INSTALLATION OF LATH, BACKER BOARD AND LATH WEEP SCREEDS. 2. YOU NEED 3/4" PENETRATION LATH FASTNERS INTO WOOD. |