Inspection Status: Correction Required
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 03/24/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - PARTIAL - AT PLAN GROUND WALL 1ST 50 + OR -. |
| 03/24/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |
| 02/08/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - PARTIAL - BENCH SEAT AT WEST WALL. |
| 02/08/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 01/20/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - PARTIAL - AT SOUTH WALL EAST SIDE. |
| 01/20/2000 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 10/08/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |
| 09/24/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - ELEVATOR SHAFT. |
| 09/24/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 08/30/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - GRADE BEAM AT S. END OF BUILDING |
| 08/30/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 08/25/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 08/25/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |
| 08/20/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - COLUMN BASE DRY PACKED |
| 08/20/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 08/17/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - WALL FTGS & COLMN FTGS OK WHEN NW COLUMN CHAIRED & CLEANED |
| 08/17/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 08/12/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - NOT READY |
| 08/12/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
IVRS - Inspection 0000* |
| 07/29/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - COL. FTS AT S.E. CORNER |
| 07/29/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 07/28/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
IVRS - Inspection 0000$ |
| 07/27/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - AT EAST SIDE |
| 07/27/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000$ |
| 07/19/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - BUILDING 4 AT EAST SIDE |
| 07/19/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |