Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.
Inspection Status: Correction Required
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 05/13/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - WALL FOR HANDICAP RAMP-SOUTH |
| 05/11/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - NORTH DOCK AT EAST SIDE. |
| 05/11/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 05/06/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - PARTIAL AT DOCKS AND RAMPS (COMPLETE STEEL AT SOUTH END OF NORTH DOCK). |
| 05/06/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 04/20/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - LINE K |
| 04/20/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 04/08/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - PERIMETER PIERS AT NORTH AND WEST WALLS. |
| 04/08/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/31/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 03/30/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - AT EAST AND PARTIAL NORTH FOOTINGS OKAY |
| 03/30/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/25/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - LINE A AND ROW 6. |
| 02/25/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |
| 02/23/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - 4-F-3S 4-F-1S 3-F-7S |
| 02/23/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PARTIAL APPROVAL |