Inspection Status: Correction Required
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/20/1999 |
PLUMBING - FINAL |
|
Correction Required |
ADDTL COMMS - 10/20/99 THE FOLLOWING ITEMS WERE THE ONLY ITEMS OBSERVED ON THIS DATE PERFORMED ON-SITE OBSERVATION FINAL INSPECTION OF THE OVERALL ITEM 03090 PLUMBING FINAL INSTALLATION TO VERIFY COMPLETION OF THREE DEFICIENT ITEMS LISTED ON PREVIOUS REPORT NUMBER 14 DATES SEPTEMBER 20,1999. A REVIEW OF THE DEFICIENT ITEMS WAS PERFORMED AND IT WAS DETERMINED THAT PROPER CORRECTIVE ACTION HAD BEEN TAKEN. THE OVERALL PLUMBING SYSTEM IS COMPLETE,FULLY OERATIONAL AND ACCEPTABLE FOR FULL OCCUPANCY OF THE PREMISES. |
| 09/20/1999 |
PLUMBING - FINAL |
|
Correction Required |
ADDTL COMMS - 11/16/99 THE FOLLOWING ITEMS WERE THE ONLY ITEMS OBSERVED ON THIS DATE. 03090 PLUMBING FINAL INSTALLATION. 1. SECOND FLOOR LADIES ROOM, WEST SIDE. THE FLUSH VALVE PIPING TO THE WATER CLOSET WAS INSTALLED OUT OF PROPER ALIGNMENT AND REQUIRES RE-PIPING. 2. THE WALL OPENINGS FOR THE WASTE PIPING AT TWO LAVATORIES IN THE SECOND FLOOR TOILET ROOMS REQUIRE ADDITIONAL MATERIAL TO FULLY ENCLOSE THE OPENING. |
| 08/24/1999 |
PLUMBING - FINAL |
|
Correction Required |
ADDTL COMMS - PERFORMED AN ON SITE OBSERVATION INSPECTION OF THE ITEM 03090 PLUMBING FINAL AS IT RELATES TO THE ISSUANCE OF A TEMPORARY CERTIFICATE OF OCCUPANCY. THE CONTRACTOR HAS TOILET ROOM FIXTURES INSTALLED AND OPERATIONAL IN AREAS THAT WOULD BE ESSENTIAL TO OCCUPANCY OF SHOPS AND OFFICES. A FEW MINOR CONDITIONS EXIST THAT WILL NOT INTERFERE WITH OCCUPANCY AT THIS TIME. ALL OF THESE MINOR ITEMS WILL BE COMPLETED BY THE FIRST OF THIS COMING WEEK. REFER TO FIELD REPORT #13 |
| 08/24/1999 |
PLUMBING - FINAL |
|
Partial Approval |
PALMER ENGINEERS INC |
| 08/20/1999 |
PLUMBING - FINAL |
|
Correction Required |
ADDTL COMMS - PERFORMED AN ON SITE OBSERVATION PARTIAL INSPECTION FOR ITEM 03090 PLUMBING FINAL FOR THE TOILET ROOMS ON THE NORTH AND WEST AREAS OF THE COMPLEX PERTAINING TO THE MOVEMENTOF FURNITURE INTO OFFICE SPACES. NUMEROUS PLUMBING FIXTURE INSTALLATIONS WERE INCOMPLETE AT THIS TIME BUT THERE WOULD BE NO INTERFERENCE WITH THE COMPLETION OF THE PLUMBING INSTALLATION CREATED BY THE PLACEMENT OF FURNITURE INTO OFFICE AND SHOP AREAS.PLACEMENT OF THE FIXTURES WILL BE PRIMARILY CONFINED TO THE TOLIET ROOM AREAS. REFER TO FIELD REPORT #12 |
| 08/20/1999 |
PLUMBING - FINAL |
|
Partial Approval |
PALMER ENG. |
| 06/15/1999 |
PLUMBING - FINAL |
|
Partial Approval |
PARTIAL APPROVAL |