Inspection Status: Correction Required
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 01/07/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - 1. ALL UNDER SLAB A.B.S PLUMBING THAT WILL BE IN CONTACT WITH CONCRETE MUST BE WRAPPED. 2. NO APPROVED SITE PLAN AVAILABLE |
| 01/07/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
IVRS - Inspection 0999* |
| 01/04/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - 1. NO PLANS OR PERMIT ON SITE. 2. PLUMBING NOT PROPERLY WRAPPED BELOW FINSIHED FLOOR. ALL ABS PLASTIC BELOW GRADE MUST BE PROTECTED FROM CONTACT WITH CONCRETE. EXPOSE ALL A.B.S PLASTIC PLUMBING TO SOIL. NOTE: CONCRETE POURED WITOUT APPROVAL. |
| 01/04/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
IVRS - Inspection 0999* |
| 12/31/1998 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - TRADE NOT COMPLETE. |
| 12/31/1998 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection 0000* |