Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Correction Required
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/1999 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. DRAWING REVISION, MOVED BLDG LINE SOUTH REINSPECTED SOIL LINES |
| 12/31/1998 |
PLUMBING - ROUGH, SOIL |
|
Denied |
DENIED |
| 12/09/1998 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. SETBACK ON SITE PLAN 25 IS INCORRECT, PLEASE SUBMIT CORRECT SETBACK BEFORE FINAL. |
| 12/09/1998 |
PLUMBING - ROUGH, SOIL |
|
Denied |
DENIED |
| 12/08/1998 |
PLUMBING - ROUGH, SOIL |
|
Correction Required |
ADDTL COMMS - 1. NEED BLDG LINES ESTABLISHED. 2. NEED A H2O STATIC TEST ON SOIL LINES. 3. CANNOT VERIFY WHAT YOUR REQUIRED SETBACK IS ON SOUTH SIDE PLAN HAS GOTTEN WET. |
| 12/08/1998 |
PLUMBING - ROUGH, SOIL |
|
Denied |
DENIED |