Inspection Status: Correction Required
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 02/24/1999 |
BUILDING PRE-SLAB |
|
Correction Required |
ADDTL COMMS - COMPLETE STEEL |
| 02/08/1999 |
BUILDING PRE-SLAB |
|
Correction Required |
ADDTL COMMS - RAMP AND STAIR FTG. |
| 02/08/1999 |
BUILDING PRE-SLAB |
|
Partial Approval |
PARTIAL APPROVAL |
| 12/11/1998 |
BUILDING PRE-SLAB |
|
Correction Required |
ADDTL COMMS - COL. LINE 2-3, COL. LINE 4-5 (BETWEEN NORTH TWO COLUMNS) |
| 12/11/1998 |
BUILDING PRE-SLAB |
|
Partial Approval |
PARTIAL APPROVAL |
| 12/08/1998 |
BUILDING PRE-SLAB |
|
Correction Required |
ADDTL COMMS - COL. LINE 3-4 (3RD BAY FROM WEST) |
| 12/08/1998 |
BUILDING PRE-SLAB |
|
Partial Approval |
PARTIAL APPROVAL |
| 12/07/1998 |
BUILDING PRE-SLAB |
|
Partial Approval |
COL. LINE 1-2 |