Permit: T98CM03389

Parcel: 14027050D

Inspection Status: Correction Required

Inspection History: BUILDING PRE-SLAB

Permit Number - T98CM03389

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Correction Required

Date Description Inspector Results Comments
02/24/1999 BUILDING PRE-SLAB Correction Required ADDTL COMMS - COMPLETE STEEL
02/08/1999 BUILDING PRE-SLAB Correction Required ADDTL COMMS - RAMP AND STAIR FTG.
02/08/1999 BUILDING PRE-SLAB Partial Approval PARTIAL APPROVAL
12/11/1998 BUILDING PRE-SLAB Correction Required ADDTL COMMS - COL. LINE 2-3, COL. LINE 4-5 (BETWEEN NORTH TWO COLUMNS)
12/11/1998 BUILDING PRE-SLAB Partial Approval PARTIAL APPROVAL
12/08/1998 BUILDING PRE-SLAB Correction Required ADDTL COMMS - COL. LINE 3-4 (3RD BAY FROM WEST)
12/08/1998 BUILDING PRE-SLAB Partial Approval PARTIAL APPROVAL
12/07/1998 BUILDING PRE-SLAB Partial Approval COL. LINE 1-2