Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/31/2001 |
ELECTRIC - FINAL |
|
Approved |
IVRS - Inspection 0000* |
| 05/30/2001 |
ELECTRIC - FINAL |
|
Not ready for Inspection |
IVRS - Inspection 0000*1)3 UNITS WEST END NOT COMPLETE YET (H20-HTRS).2)SOME UNITS NOT ENERGIZED.3)RE-CALL WHEN WIRING IS COMPLETE AND ALL UNITS ENERGIZED FOR (POWER CHECK-OUT). |
| 05/23/2001 |
ELECTRIC - FINAL |
|
Partial Approval |
IVRS - Inspection 0000*COMPLETE WATER HEATER INSTALLATIONS. |
| 04/26/2001 |
ELECTRIC - FINAL |
|
Partial Approval |
IVRS - Inspection 0000* OK TO CLEAR AND CABLE DROP TEMP POWER FOR UNITS: 3101-3106, 3201-3206 |