Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2004 | GRADING - FINAL | Approved | ||
| 08/29/2003 | GRADING - FINAL | Denied | 1. Lot grading is not graded per plan specification for Lot types A, B and C as indicated on Page 1 of the Grading Plan. Type "A" Lots 6, 69,76 and 78 do not drain to the front. Type "B" Lots 1-5, 8-17 and 52 do not drain to the rear. Type "C" Lots 7 and 49-51 do not drain to the rear. 2. Erosion damage is present where lots 7 and 78 drainage has been altered to discharge at the side of the lots. 3. Erosion damage was noted on the east bank of the retention/detention basin. The slope has not been re-vegetated or stabilized. 4. The retention/detention basin is not percolating after rain events. Standing water in this basin is growing algae and is creating prime habitat for breeding mosquitoes. 5. The drainage channel between lots 46 and 47 is not constructed per Detail N, Page 2. The bottom width is 7.5' of the required 15' shown on the Grading Plan. 6. The sidewalk at the southeast corner of Calle Alvord and Avenida Bodega has not been completed. (The City of Tucson Water Well Site). 7. Slope stabilization, backfill at perimeter footing and construction material clean up has not been completed at the outer edge of construction, behind lots 1-17. 8. The rock rip rap in the drainage easement at the northwest corner of lot 37 has been installed at an elevation that restricts the flow under the wall opening. The rock rip rap needs to be removed and placed to eliminate any drainage flow restriction. |