Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T98BU00587
Inspection Description - GRADING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2005 | GRADING - FINAL | Approved | The existing conditions requested to be addressed are from John Bruckmeier's last inspection. On this date, I spoke with the land developer Scott with US/Linear homes. He explained that Matt Flick has approved the 36" pipe vs. the approved plan which has a 42" pipe for drainage. The second comment was regarding excessive sediment down stream of the sidewalk scupper between lots 112 & 113 has been removed. Final Grading has been approved. | |
| 03/19/2003 | GRADING - FINAL | Denied | FINAL GRADING DENIED. 1. PROVIDE AS-BUILT DRAWINGS AND DRAINAGE REPORT CALCULATIONS FOR REVISIONS MADE TO THE STORM DRAINAGE PIPE BETWEEN LOTS 107 & 108. THE PIPE IS ONLY 36" OF THE REQUIRED 42" AS INDICATED ON THE GRADING PLAN. 2. REMOVE CONSTRUCTION SEDIMENT DEPOSITED IMMEDIATELY DOWNSTREAM OF THE SIDEWALK SCUPPER ON PLACITA DEL COMIENZO BETWEEN LOTS 112 & 113. |
|
| 10/22/2002 | GRADING - FINAL | Denied | FINAL GRADING DENIED. LOCATION: CORTE ALBOR - BETWEEN LOTS 107 & 108 1) THE STORM DRAINAGE PIPE IS ONLY 36" OF THE REQUIRED 42" INDICATED ON THE GRADING PLAN. PROVIDE REVISED DRAWINGS AND CALCULATIONS TO SHOW THAT DRAINAGE REQUIREMENTS HAVE BEEN MET. 2) CATCH BASIN INLET HAS CONCRETE WASH OUT BUILD UP. REMOVE ALL SEDIMENT AND CONSTRUCTION DEBRIS FROM DRAINAGE AREAS. 3) EROSION AT THE BASE OF THE ROCK RIP RAP PROVIDED AT THE DISCHARGE END OF THE 36" STORM DRAIN. REPAIR EROSION DAMAGE. LOCATION: UPSTREAM OF CORTE ALBOR - BETWEEN LOTS 112 &113. 1) EROSION AT THE UPSTREAM SIDE OF THE ROCK RIP RAP AT THE INLET TO THE 30" SRP. PLEASE REPAIR THE EROSION DAMAGE. LOCATION: PLACITA DEL COMIENZO BETWEEN LOTS 112 &113. 1) REMOVE CONSTRUCTION SEDIMENT DEPOSITED DOWNSTREAM OF THE SIDEWALK SCUPPER |