Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Correction Required
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 02/22/2000 |
PLUMBING - GAS PRESSURE TEST |
|
Correction Required |
ADDTL COMMS - 1. MUST HAVE GAS SYSTEM REVISED DRAWING APPROVED BY CITY PLAN CHECK |
| 02/22/2000 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 12/02/1999 |
PLUMBING - GAS PRESSURE TEST |
|
Correction Required |
ADDTL COMMS - NOT READY FOR INSPECTION |
| 12/02/1999 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 05/23/1999 |
PLUMBING - GAS PRESSURE TEST |
|
Denied |
IVRS - Inspection 0000* |
| 05/17/1999 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection 0000* |