Permit: T97CM00198

Parcel: 120060540


Addresses:

119 E PRESIDENT ST

Inspection Status: Correction Required

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
02/16/1999 EXCAVATION/LAYOUT REBAR & ZON Correction Required ADDTL COMMS - THE PROJECT WAS INSPECTED FOR THE INTERIOR, ADDITION, AND A PORCH (AT FRONT) WHICH WAS ADDED, AFTER A PERMIT FOR THE ADDITION WAS ISSUED, TO THE PERMIT. SEVERAL INSPECTORS VISITED THE SITE FROM 1997-1999. SOME CONFUSION ENSUED, HOWEVER; I INSPECTED THE FOUNDATION WORK INSIDE AND OUT. BASED ON THE ABOVE INFORMATION I REQUEST THE FINALS BE ACCEPTED AND THE PROJECT CLOSED.
05/01/1998 EXCAVATION/LAYOUT REBAR & ZON Correction Required ADDTL COMMS - 1. NEED APPROVED PLANS AND REVISION FOR 10X 35 FRONT PORCH
05/01/1998 EXCAVATION/LAYOUT REBAR & ZON Denied DENIED
04/16/1997 EXCAVATION/LAYOUT REBAR & ZON Correction Required ADDTL COMMS - THIS PROJECT - FOUNDATION HAS ALREADY BEEN POURED W/O INSP, THERE ARE NUMEROUS ERRORS IN THE FRAMING, WIRING, AND PLBG ALREADY INSTALLED. I CALLED HENRY DURAZO AND REQUESTED HIS ASSISTANCE IN THIS INSPECTION. MR. DURAZO MANAGED TO INFORM THE HOMEOWNER OF THE EXTENT OF THE MISCELLANEOUS ERRORS COMMITTED IN THE CONTSTRUCTION OF THE ADDITION.
04/16/1997 EXCAVATION/LAYOUT REBAR & ZON Denied DENIED