Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Correction Required
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 02/16/1999 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - THE PROJECT WAS INSPECTED FOR THE INTERIOR, ADDITION, AND A PORCH (AT FRONT) WHICH WAS ADDED, AFTER A PERMIT FOR THE ADDITION WAS ISSUED, TO THE PERMIT. SEVERAL INSPECTORS VISITED THE SITE FROM 1997-1999. SOME CONFUSION ENSUED, HOWEVER; I INSPECTED THE FOUNDATION WORK INSIDE AND OUT. BASED ON THE ABOVE INFORMATION I REQUEST THE FINALS BE ACCEPTED AND THE PROJECT CLOSED. |
| 05/01/1998 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - 1. NEED APPROVED PLANS AND REVISION FOR 10X 35 FRONT PORCH |
| 05/01/1998 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
DENIED |
| 04/16/1997 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Correction Required |
ADDTL COMMS - THIS PROJECT - FOUNDATION HAS ALREADY BEEN POURED W/O INSP, THERE ARE NUMEROUS ERRORS IN THE FRAMING, WIRING, AND PLBG ALREADY INSTALLED. I CALLED HENRY DURAZO AND REQUESTED HIS ASSISTANCE IN THIS INSPECTION. MR. DURAZO MANAGED TO INFORM THE HOMEOWNER OF THE EXTENT OF THE MISCELLANEOUS ERRORS COMMITTED IN THE CONTSTRUCTION OF THE ADDITION. |
| 04/16/1997 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
DENIED |