Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
| Date |
Description |
Inspector |
Results |
Comments |
| 09/14/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-Work continues steel plates placed on roadway I called contractor to bring out a bump sign. |
| 09/07/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity |
| 08/29/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity |
| 08/16/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired. |
| 08/03/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired. |
| 07/15/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired 6/12/22. |
| 06/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-Talked with contractor they haven’t started and the are going to renew permit. |
| 06/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-Pre-con with Super Drain owner on phone they will start next week after notifications. |
| 10/17/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-Work completed temporary patch placed permit expired I spoked with Juan from Super Drain to renew the permit. |
| 09/26/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-Work completed slurry seal needed. |
| 05/20/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Continued-No activity |
| 11/16/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
Work completed temporary patch placed. |
| 01/25/2023 |
TRSP - ROW - Recurring |
|
Re-inspection required |
Work completed temporary patch placed. |
| 06/23/2023 |
TRSP - ROW - Recurring |
|
Re-inspection required |
|