Inspection History Details
Inspection Status: Re-inspection required
Inspection History: TRSP - ROW - Recurring
Permit Number - T22RW01430
Inspection Description - TRSP - ROW - Recurring
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued | |
| 09/21/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. Set up to what we agreed to. Right lane closure. Sidewalk closed due to installing of vaults in sidewalk. | |
| 09/14/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Construction is ongoing at this time. | |
| 09/15/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
| 09/13/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - All work is in progress at this time. | |
| 09/14/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. I spoke with Cuba and Francisco today about the VPs being set 24 hours a day. They will be pulling the traffic control down at night to open up the lane. | |
| 08/24/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Installing TEP vaults in the sidewalk. | |
| 09/13/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
| 08/23/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued | |
| 08/24/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. I gave contractor permission to leave lane closure up 24 hours. I came thru on 8-21-22 at 5pm and pedestrians were walking in roadway because of sidewalk closures. | |
| 08/22/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Sidewalk has new manholes being installed. Chain link Fence around excavations. | |
| 08/23/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
| 08/05/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Placing conduit in concrete then backfilling with ab daily | |
| 08/22/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. Traffic control is good. Waiting on updated tcp. Flaggers on site to help with pedestrian traffic | |
| 08/02/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Backfilling as they go. Plates on any thing left open. | |
| 08/05/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. Flaggers on site to assist pedestrians around job site. Traffic control is correct | |
| 10/13/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued | |
| 10/13/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control needs maintenance. Crew set up signs and vp’s that have were down. I asked them to check before and end of shift. | |
| 09/26/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Correction Required. Got a call last night about fence panel over new manholes. Will be placing manhole covers or a plate across closed sidewalk | |
| 09/26/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. Traffic control is ok. | |
| 07/18/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection | |
| 08/02/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. Waiting on a revision to TCP. We have sidewalk CLOSED. Contractor needs traffic lane to remove spoils from trench. They are working 10 hour days | |
| 11/07/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 01/11/2023 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 01/19/2023 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 02/10/2023 | TRSP - ROW - Recurring | Passed | ||
| 11/08/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 11/10/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 11/23/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 11/28/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 12/07/2022 | TRSP - ROW - Recurring | Complete (Recurring) | ||
| 12/14/2022 | TRSP - ROW - Recurring | Complete (Recurring) |