Permit: T22RW00370

Parcel: 110100400


Addresses:

5001 E GLENN ST

Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Date Description Inspector Results Comments
03/23/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going. Plates have all been recessed.
04/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading is in the roadway. Flaggers are being utilized.
03/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
04/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Irritating has been moved to the side of the road.
03/11/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
04/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading has been removed from roadway.
03/07/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
04/08/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - All barricading has been moved to side of road.
03/02/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pot holing in Glen. Traffic control is set up per plan. No issues.
04/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading has been moved to the side of the road. Barricading is not affecting traffic at this time.
02/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going. Flagman being utilized. No issues.
03/23/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading in place per plan. Automated flaggers are now being used.
10/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Two sidewalk panels are broken. The curb height does not follow the development plan. Backstops are needed at the back of the wheelchair ramps. And it appears that the asphalt is failing right next to the curb.
09/26/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Entrance into new subdivision still needs to be paved.
09/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - The entrance into new development still needs to be paved.
09/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - The paving from the north edge of Glen Street to the right of way still needs to be completed.
08/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Sidewalk on southside of Glen has been poured. The sidewalk on the north side of Glenn’s been cut. Still need to pave to the right of way at the new entrance.
08/11/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Sidewalk on the southside of Glenn still needs to be re-poured. The sidewalk on the north side I’m going has been cut back to alleviate the drop off. The entrance into the property needs to be paved up to the right of way.
08/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
07/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Sidewalk still needs to be cut on the east end of project northside of Glenn. Microsealing still needs to be done where the new curb was installed. Sidewalk on the southside of Glen has to be rehabilitated. Paving from gland to the right of way still needs to be done.
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Barricading is being set up. Plates in the road I’ve been recessed.
03/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
07/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Sidewalk still has not been removed.
07/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - I talked to Christos the owner of the property. I told him that that sidewalk had to be cut where John and I discussed. He wants to do some other construction in that area. I told him he needs to have an engineer draw it up and have it reviewed by the city. The new construction work will be done under a different permit.
07/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Talk to John Dominguez about the removal of the sidewalk. He is going to remove the sidewalk at an agreed location. And then fill in that area with dirt. This will alleviate any pedestrian or wheelchair issues. The striping has been completed. The only few things left is Microsealing needs to be done in the bike lane, the paving needs to be finished to the right of way and the sidewalk on the other side needs to be rehabilitated.
07/13/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Area has been re-paved. The striping needs to be rehabilitated. They are building the new sewer manhole. The sidewalks and the ramps are all within specifications. I am concerned about the east end of the sidewalk. I believe they should put a guard rail up. I told the contractor that they need to go back to the designer of this project. I will call the contractor again to see what is going on with this. There is a big drop off right at the edge of sidewalk.
07/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - The East End of the new sidewalk has a drop off at the next property. I told the concrete guys that this had to go back to the designers of the project. They taper down the height of the sidewalk and angled it away from the drop off that’s at the next property. I did tell them they had to go back to the designers for a redesign.
07/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Glen Street still has plates in the road. The sidewalk is being poured. The roadway still needs to be saw cut and re-paved. The area next to the new curb needs to be micro sealed for the bike lane.
07/05/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - I did a Forms inspection on the sidewalk and the wheelchair ramps going into the new subdivision. The sidewalks and the ramp are right at 2%.
07/01/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - I did a forms inspection on the wheelchair ramps on this project. They were out of spec. I told the guys out in the field and I got a call into the owner of the company. The plans call for the pag standards. It was more than 2% from the back of the sidewalk form to the back of curb.
06/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Had a meeting with John from Dominguez. He is going to do the Tee Top patches where the trenches are located and re-pave that section. The areas next to the curb he will re-pave and then microseal the bike line. All of the trenches were well inside of the area milled.
09/26/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Temporary fence still in place behind sidewalk.
06/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
09/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Temporary fence still in place behind sidewalk. All other barricading has been removed.
02/11/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Call John Dominguez from earthmovers, I let him know that the roadway on Glenn is not under a moratorium. He will have to do the micro seal.
03/07/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - No issues with barricading. Flagman on each side.
05/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
09/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - The barricading has been removed from the roadway. The only barricading left is the temporary fence along in North edge of the north sidewalk of Glenn Street. There’s also sidewalk closed signs on both sides of the new sidewalk on the north side of Glenn street.
05/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
08/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Sidewalk closed sign still up. Temporary fence still in place. Barricading has been removed from roadway.
05/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
07/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
04/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
07/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
04/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
06/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading has been moved to the side of the road.
04/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
05/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan. Flagmen are being utilized again.
04/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
05/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
04/08/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Plates are still in the roadway. Sidewalk needs to be rehabilitated.
05/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
04/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Plates are still in Roadway.
05/05/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading has been removed from Road for now
03/30/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work on going.
04/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Had Precon today. I explained to him working hours, keeping everything ADA for the sidewalk and ramps and the roadway restoration. Dashboard does not show this road under moratorium, but the road is in very good shape. He is going to have one patch and he’s going to mill in between them. I checked with James Castaneda about this road being under moratorium. He says it is not but a micro surface was recently done. I told contractors that I will let them know if this is a moratorium or not. He is going to do his notifications today and start next week. Trafficade is going to do the barricading.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricading set up to the traffic control plan. Flaggers are being utilized. No concerns at this time.
11/28/2022 TRSP - ROW - Recurring Complete (Recurring)
08/16/2023 TRSP - ROW - Recurring Complete (Recurring)