Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22RW00250

Parcel: Unknown


Addresses:

519 N ALVERNON WY


Inspection Status: Passed

Inspection History: TRSP - ROW - Recurring

Permit Number - T22RW00250

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Passed

Date Description Inspector Results Comments
05/16/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - Site passes final ROW inspection. Landscaping restored.
03/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex placing r/f on swf pole. Light to be installed today. Work should be done Thursday at latest.
05/16/2022 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
03/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Quail setting up early asked them to wait until 0900
03/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex poured concrete and slurry. Waiting for slurry to set up to set boxes. Sam k with deih onsite for placement. WTI took strength cylinders for caisson. Remaining backfill to be done with native and visual inspection for 10” and around boxes.
03/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. Quail setting up early asked them to wait until 0900
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex preparing for pour at 1330. Sam deih inspecting caisson and trenches.
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
03/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex vacuum trenching for caisson. Rocks are unable to be picked up by vacuum velex trying to figure a solution to reach depth they are +\- 3.5’ above final depth.
03/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
03/08/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex trenchin under sidewalk for fiber.
03/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
03/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pedestrian walkway to att in place until completion of project. Met with Dan to discuss this morning
03/08/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/23/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Yeah row con with Michael smith velex James deih and Sam deih. Notified to call sun Tran over relocating bus stop. Must have pedestrian access at all times around site. Traffic control plan approved. Remove old pole and place swf pole. Notifications set to be sent 5 days prior to start of construction.