Permit: T22RW00185

Parcel: 11105094B

Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Date Description Inspector Results Comments
06/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway. Tucson water notified
05/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
05/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
03/16/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
03/02/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - New water service has been installed. Temporary asphalt patch still in place
02/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Service has been installed. Temporary asphalt patch still in place
02/07/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Water line installed. Temporary asphalt patch in place
09/06/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
08/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Underground water repairs completed. Temporary asphalt patch still in roadway
07/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Temporary asphalt patch still in roadway
07/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Underground water work has been completed. temporary asphalt patch still in place
01/11/2023 TRSP - ROW - Recurring Complete (Recurring)
01/31/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No work on permit. Area has been marked out for work
02/14/2023 TRSP - ROW - Recurring Passed