Inspection Status: Passed
Inspection History: TRSP - ROW - Recurring
| Date |
Description |
Inspector |
Results |
Comments |
| 06/06/2022 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-EXCAV GENERAL INSPECTION - Landscaping fixed by vertical one. Meter placed. ROW passes final inspection. |
| 05/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Landscaping restored. Fiber vault east in front of pole needs material brought flush with box. Bolts need to be placed to secure lid. |
| 06/06/2022 |
TRSP - ROW - Recurring |
|
Passed |
TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. |
| 03/10/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |
TDOT-EXCAV GENERAL INSPECTION - Pre con with vertical one, deih, truenet, and southwest barricades. Waiver request due to be sent in for bore route to be in landscaping instead of street. 8” water line runs 3’ off of curb east from north to south. Does not give 5’ horizontal clearance per spec. Storm drain runs 7’ east of water line so bore could not be placed between. Best viable option per truenet is through the landscaping. James deih and Neil vertical one will place waiver to move pedistole 15’ west of plans location to keep near other utilities and out of public view. Southwest barricades to be added to plans and submit traffic control plan. |
| 05/24/2022 |
TRSP - ROW - Recurring |
|
Re-inspection required |