Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2022 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | ||
| 03/15/2022 | FIRE SPKLR - UG, PIPING, HYDRO | Prior to Final Inspectn | Backflow needs to be monitored before final can be given. 2. The flow still need to test the flow it needs to be 1500 |
|
| 02/25/2022 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Waiting on test cert and letter releasing TFD from liability 205 psi |
|
| 02/23/2022 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | When I arrived on site the system had 190 psi on the guage. We need 200psi for 2 hours. |