Inspection History Details
Inspection Status: Passed
Inspection History: PDSD Building Division - Site Excavation/Layout/Rebar
Permit Number - T22CM08135
Inspection Description - PDSD Building Division - Site Excavation/Layout/Rebar
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/11/2023 | PDSD Building Division - Site Excavation/Layout/Rebar | Passed | ||
10/18/2023 | PDSD Building Division - Site Excavation/Layout/Rebar | Not Ready | 10/18/23: bollards not ready for inspection, reinforcing not installed. | |
10/19/2023 | PDSD Building Division - Site Excavation/Layout/Rebar | Re-inspection required | 10/18/23: bollards not ready for inspection, reinforcing not installed. 10/19/23: bollards not ready for inspection. Remove all dirt from the top of the concrete in the bottom of the footing so as the new concrete will bond and make a cold joint. |
|
10/20/2023 | PDSD Building Division - Site Excavation/Layout/Rebar | Partial Pass | 10/20/23: all bollards approved, concrete mat outside storage area approved. | |
11/17/2023 | PDSD Building Division - Site Excavation/Layout/Rebar | Passed |