Inspection Status: Not Applicable
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 08/16/2023 |
BULD - Electrical Clearance |
|
Not Applicable |
duplicate |
| 08/16/2023 |
BULD - Electrical Clearance |
|
Re-inspection required |
NR, plans must be revised to accurately reflect installation, 100A breaker and 125A sub panel? Incomplete labels |
| 09/15/2023 |
BULD - Electrical Clearance |
|
Passed |