Inspection Status: Not Ready
Inspection History: COT - RSBU - Interior Shear Bracing
| Date |
Description |
Inspector |
Results |
Comments |
| 07/12/2023 |
COT - RSBU - Interior Shear Bracing |
|
Not Ready |
7/12/23 Not ready done at intermediate |
| 10/31/2024 |
COT - RSBU - Interior Shear Bracing |
|
Re-inspection required |
10-31-24, not ready. Seal off all penetrations on top plates with fire foam. Sleeve any intended underground plumbing prior to pouring concrete slab, reschedule intermediate inspection when ready. |
| 11/29/2024 |
COT - RSBU - Interior Shear Bracing |
|
Passed |
Inspection passed on 11/12/24 under another entry |
| 11/12/2024 |
COT - RSBU - Interior Shear Bracing |
|
Passed |
11-12-24, interior shear wall approved. |