Inspection Status: Not Ready
Inspection History: COT - RSME - Mechanical Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - RSME - Mechanical Final |
|
Not Ready |
|
| 04/20/2023 |
COT - RSME - Mechanical Final |
|
Not Ready |
4/20/23: Not ready for inspection, workers in the house. |
| 04/21/2023 |
COT - RSME - Mechanical Final |
|
Not Ready |
|
| 07/18/2023 |
COT - RSME - Mechanical Final |
|
Re-inspection required |
7/18/23: Landscaping not done. A/c unit must meet proper clearances according to manufacturer specs, base for a/c unit must be 3" above grade. Add outlet receptacle to kitchen countertop. Outlets must be within 24" of countertop edge per code E3901.4.1 of 2018 IRC. |
| 07/24/2023 |
COT - RSME - Mechanical Final |
|
Passed |
|