Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
Permit Number - T22CM06021
Inspection Description - COT - RSBU - Excavation/Rebar/Zoning
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | Not Ready | ||
| 04/25/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 4/25/24: Plans are not approved by city. Set backs not per plan. STOPPED INSPECTION. | |
| 08/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 4/25/24: Plans are not approved by city. Set backs not per plan. STOPPED INSPECTION. 8/28/24: revision will need to be made to set of plans in order to meet DDO requirements. Not ready for Preslab. |
|
| 09/12/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 9/12/24; Plumbing is running inside footing. Remove plumbing from footing and place in slab area. | |
| 09/17/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required | 9/17/24: no access called and knocked on door. | |
| 09/20/2024 | COT - RSBU - Excavation/Rebar/Zoning | Re-inspection required (with fee) | 4/25/24: Plans are not approved by city. Set backs not per plan. STOPPED INSPECTION. 8/28/24: revision will need to be made to set of plans in order to meet DDO requirements. Not ready for Preslab. 9/12/24; Plumbing is running inside footing. Remove plumbing from footing and place in slab area. 9/17/24: no access called and knocked on door. 9/20/24: per previous notes. Plumbing is running inside footing. Remove plumbing from footing and place in slab area. Reinforcement must have a 3" clearance from earth on all sides. |
|
| 10/23/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed |