Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Building Above Ceiling |
|
Not Ready |
|
| 01/18/2023 |
COT - LCBU - Building Above Ceiling |
|
Partial Pass |
hard lid ceiling are good and can be Sheetrocked. drop ceiling are being installed and are not ready for inspection. |
| 02/07/2023 |
COT - LCBU - Building Above Ceiling |
|
Partial Pass |
seismic wires need to be every 4 ft on longitudinal rails ok to install tiles on edges only |
| 02/22/2023 |
COT - LCBU - Building Above Ceiling |
|
Partial Pass |
Rooms 110, 117, 118, & 120 are complete. Okay to install ceiling tiles in these rooms. Room 106 the electrical and mechanical are in progress. Will call for inspection when ready. |
| 02/24/2023 |
COT - LCBU - Building Above Ceiling |
|
Partial Pass |
grid for grid ceilings is installed. Wires for light fixtures are in place. Fixtures are still about 2 weeks for delivery. Okay to install tiles in ceiling. |
| 11/01/2023 |
COT - LCBU - Building Above Ceiling |
|
Passed |
|