Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 10/18/2023 |
COT - LCBU - Building Final |
|
Re-inspection required |
10/18/23: purlin connection to beam calls for 8 screws only four installed throughout all carports, all junction boxes are not made up and missing covers. |
| 10/18/2023 |
COT - LCBU - Building Final |
|
Re-inspection required |
10/18/23: purlin connection to beam calls for 8 screws only four installed throughout all carports, all junction boxes are not made up and missing covers. |
| 11/01/2023 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 11/01/2023 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 11/03/2023 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 11/03/2023 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 11/07/2023 |
COT - LCBU - Building Final |
|
Passed |
|
| 11/07/2023 |
COT - LCBU - Building Final |
|
Passed |
|