Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 01/04/2023 |
COT - HCBU - Framing |
|
Partial Pass |
framing at north hallway to stock room approved |
| 01/09/2023 |
COT - HCBU - Framing |
|
Partial Pass |
replace all spliced studs in restroom and else where on site. OK to one side all framing with wallboard. |
| 01/12/2023 |
COT - HCBU - Framing |
|
Partial Pass |
all framing in new divided room approved |
| 01/27/2023 |
COT - HCBU - Framing |
|
Partial Pass |
Lobby skylight framing approved |
| 02/01/2023 |
COT - HCBU - Framing |
|
Passed |
lobby skylight radius framing approved. All framing at this TI is complete |
| 03/02/2023 |
COT - HCBU - Framing |
|
Passed |
|
| 12/16/2022 |
COT - HCBU - Framing |
|
Partial Pass |
demising wall framing partially approved. OK to one-side rock |
| 12/19/2022 |
COT - HCBU - Framing |
|
Partial Pass |
|
| 12/22/2022 |
COT - HCBU - Framing |
|
Partial Pass |
framing at entrance ceiling furr-out and soffit approved |