Inspection Status: Passed
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 02/08/2023 |
BULD - Electrical Clearance |
|
Passed |
|
| 04/18/2025 |
BULD - Electrical Clearance |
|
Re-inspection required |
Not ready. Need access to the site. No one was home to verify equipment and do the inspection. 4/18/2025 |
| 05/05/2025 |
BULD - Electrical Clearance |
|
Re-inspection required |
Field installations are not per the approved drawings. 5/5/2025 |
| 07/17/2025 |
BULD - Electrical Clearance |
|
Passed |
Approved solar - DGC Clearance to TEP is required for the solar meter |