Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Building Final
Permit Number - T22CM04680
Inspection Description - COT - LCBU - Building Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCBU - Building Final | Not Ready | ||
01/04/2024 | COT - LCBU - Building Final | Partial Pass | Partial pass. Pending water cloronation report and air balance report. Okay for level 4 TCO. 1/4/2024 Both have been submitted. EWS | |
05/12/2023 | COT - LCBU - Building Final | Partial Pass | 5-12-23: Partial for Phase One. | |
12/05/2023 | COT - LCBU - Building Final | Not Ready | ||
12/19/2023 | COT - LCBU - Building Final | Partial Pass | 12/19/23 ok for level 4 TCO |