Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 01/31/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
partial approval for UG conduits along north side for light pole bases and island conduit from building, ok to cover |
| 03/06/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
partial approval for NE & NW corners ok to install plywood |
| 03/15/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
for secondary conduits from transformer to equipment room |
| 03/17/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
partial approval for hard lids in restrooms, soffit areas portion walls in back of house, ok to install plywood |
| 03/20/2023 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
partial approval for south side UG for light pole bases |
| 04/25/2023 |
COT - HCEL - Electrical Progress |
|
Not Ready |
pull all outlets, to verify grounding on all boxes |
| 06/22/2023 |
COT - HCEL - Electrical Progress |
|
Passed |
|