Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - T22CM04501
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
01/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | partial approval for building internal caissons, ok to place concrete | |
01/12/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | partial approval for building footers ok to place concrete | |
01/31/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | partial approval for screen wall on north side | |
02/24/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | partial approval for 4 light pole bases and 3rd lift on canopy columns | |
03/02/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 3/1/23 forth lift on canopy columns ok to place concrete | |
08/15/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed |