Permit: T22CM04426

Parcel: 13631002S


Addresses:

4110 S HOUGHTON RD


Inspection Status: Partial Pass

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM04426

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/07/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 6/7/24: partial for column footings 5 at north east corner exterior and 3 at south west corner exterior.
06/28/2024 COT - LCBU - Excavation/Rebar/Zoning  Passed 6/28/24: Passed all monolithic footings/slab on grade areas on outside northeast corner, southwest corner, and interior footings for column posts. Okay to proceed with concrete pour.