Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: RSBU - Building Final
Permit Number - T22CM04389
Inspection Description - RSBU - Building Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | RSBU - Building Final | Not Ready | ||
01/17/2024 | RSBU - Building Final | Partial Pass | ok for TCO level 3 | |
02/12/2024 | RSBU - Building Final | Partial Pass | Ok for TCO 4 | |
02/14/2024 | RSBU - Building Final | Partial Pass | TCO 4 | |
02/15/2024 | RSBU - Building Final | Not Ready | ||
02/16/2024 | RSBU - Building Final | Partial Pass | ||
02/20/2024 | RSBU - Building Final | Passed | OK for CofO | |
12/08/2023 | RSBU - Building Final | Not Ready | ||
12/11/2023 | RSBU - Building Final | Not Ready | 12/11/23: UV coat all piping on exterior of home. All appliances need to be installed to ensure proper support, drainage and connections. |