Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - T22CM03945
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/12/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. | |
04/16/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. |
|
04/17/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall 0-2’ AFF west side of project reinforcement per plan ok to grout. |
|
04/22/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. |
|
04/25/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. 4/25/24: west site wall 0'-84' south and 0'-108' north of sw opening, 108'-240' North of opening. |
|
04/30/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. 4/25/24: west site wall 0'-84' south and 0'-108' north of sw opening, 108'-240' North of opening. 4/30/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west 4/30/24: south side wall east of job entrance 0-4' AFF. CMU wall |
|
05/02/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. 4/25/24: west site wall 0'-84' south and 0'-108' north of sw opening, 108'-240' North of opening. 4/30/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west 4/30/24: south side wall east of job entrance 0-4' AFF. CMU wall 5/2/24: north east wall at site entrance 0-4' AFF ok to grout, south east wall at site entrance ok to top out. |
|
05/13/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. 4/25/24: west site wall 0'-84' south and 0'-108' north of sw opening, 108'-240' North of opening. 4/30/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west 4/30/24: south side wall east of job entrance 0-4' AFF. CMU wall 5/2/24: north east wall at site entrance 0-4' AFF ok to grout, south east wall at site entrance ok to top out. 5/13/24: no inspection needed. |
|
05/30/2024 | COT - HCBU - Building Progress | Partial Pass | 4/12/24: 500' of CMU Stem wall, screen wall on south side of project approved by third party inspector. 0-2' AFF. 4/16/24: 446' of CMU Screen wall south side of project. 0-3' AFF. Approved by third party inspector. 4/17/24: 216' of CMU Screen wall south side of project reinforcement per plan ok to grout and cap. 216' of CMU Stem wall west side of project reinforcement per plan ok to grout. Partial approval from HCS to approximately 60% of distance to building OK to cover 4/22/24: partial approval from HCS to 75% of distance to building ok to cover. 4/25/24: west site wall 0'-84' south and 0'-108' north of sw opening, 108'-240' North of opening. 4/30/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west 4/30/24: south side wall east of job entrance 0-4' AFF. CMU wall 5/2/24: north east wall at site entrance 0-4' AFF ok to grout, south east wall at site entrance ok to top out. 5/13/24: no inspection needed. 5/30/24: 2" pvc main from south west corner of building to 180' west of building pending point of connection at backflow preventer. Ok to backfill. Shading required |