Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM03945

Parcel: 14036007A


Addresses:

4785 E VALENCIA RD


Inspection Status: Passed

Inspection History: COT - HCEL - Electrical Underground 

Permit Number - T22CM03945

Inspection Description - COT - HCEL - Electrical Underground 

Inspection Status - Passed

Date Description Inspector Results Comments
02/01/2024 COT - HCEL - Electrical Underground  Passed
02/27/2024 COT - HCEL - Electrical Underground  Partial Pass Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
03/05/2024 COT - HCEL - Electrical Underground  Partial Pass
03/13/2024 COT - HCEL - Electrical Underground  Partial Pass
COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
05/01/2024 COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
5/1/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west
05/03/2024 COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
5/1/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west
5/3/24: underground electrical to monument sign complete ok to backfill.
05/28/2024 COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
5/1/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west
5/3/24: underground electrical to monument sign complete ok to backfill.
5/28/24: electrical underground for communication (1)4" from building south west corner to north west corner of construction site. Ok to backfill.
05/30/2024 COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
5/1/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west
5/3/24: underground electrical to monument sign complete ok to backfill.
5/28/24: electrical underground for communication (1)4" from building south west corner to north west corner of construction site. Ok to backfill.
5/30/24: electrical underground for communication (1)4" from north west corner of construction site to first column at CMU wall at north west side of project site ok to backfill progress areas. Shading required
06/04/2024 COT - HCEL - Electrical Underground  Partial Pass 2/27/24 - Partial for underground electrical conduits from the rear of building to the warehouse entry gate and the 2 front parking lot light poles
3/5/24 partial for secondaries, approximately 20 feet from proposed transformer site to building risers OK the shade and cover two conduits
3/13/24 partial approval for underground for monument sign to first light pole to the east OK to cover
3/18/24: partial approval for underground electrical for west end monument sign. Pending 400' stretch to building.
4/25/24:secondaries complete to transformer location ok to backfill. Primary conduit ok to backfill from transformer to south west corner of job site.
5/1/24: Partial approval for underground fiber to 2 1/2 inch conduit from pole box to front of building and 4 inch to from same location to first curb to the west
5/3/24: underground electrical to monument sign complete ok to backfill.
5/28/24: electrical underground for communication (1)4" from building south west corner to north west corner of construction site. Ok to backfill.
5/30/24: electrical underground for communication (1)4" from north west corner of construction site to first column at CMU wall at north west side of project site ok to backfill progress areas. Shading required
6/4/24: (1)4" from southwest corner of CMU wall to north west corner of CMU wall. Ok to backfill progress areas. Ok to continue to exact communication box
06/18/2024 COT - HCEL - Electrical Underground  Partial Pass 6/18/2024. Looked at G.E.C at southeast corner.
07/22/2024 COT - HCEL - Electrical Underground  Not Ready 7/22/24: not ready
07/23/2024 COT - HCEL - Electrical Underground  Not Ready 7/23/2024 provide 48" to the top of pipe.
07/25/2024 COT - HCEL - Electrical Underground  Partial Pass X1 4” conduit schedule 40. At 48” depth. Spare primary (J2) for TEP approximately 250’ stubbed out of site wall and just passed the property line on the north end. Okay to backfill progress areas. Shading required. 7/25/2024
07/30/2024 COT - HCEL - Electrical Underground  Partial Pass Stubbed out from site wall approximately 50’ to J2 Box. From J2 to entry of property pipe was moved 10’ east from steak. Out of easement. Per TEP requirements. Okay to backfill progress areas. Shading required. 7/30/2024
08/27/2024 COT - HCEL - Electrical Underground  Partial Pass From J2 box about 420’ to transformer (VBC 3 ) across trash enclosure at circle K. All bored at 55”. 8/27/2024