Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2025 | COT - HCBU - Building Final | Passed | 12/2/24: exterior receptacles must be WR GFCI, exhaust fan in office bathroom no power, GFCI required at break room outlets, dishwasher must be properly installed/supported, overflow switch required at air handlers, supports at water heater copper pipes must be coated, Bathroom signage must be installed at time of inspection, condenser unit tripped breaker multiple times during inspection. OK FOR LEVEL 2 TCO. 12/13/24: corrections have been made. Pending conditions. 12/20/24: ok for level 4 TCO 1/8/25:Building complete. Development Package still open and needs final inspections. |
|
| 12/02/2024 | COT - HCBU - Building Final | Partial Pass | 12/2/24: exterior receptacles must be WR GFCI, exhaust fan in office bathroom no power, GFCI required at break room outlets, dishwasher must be properly installed/supported, overflow switch required at air handlers, supports at water heater copper pipes must be coated, Bathroom signage must be installed at time of inspection, condenser unit tripped breaker multiple times during inspection. OK FOR LEVEL 2 TCO. | |
| 12/13/2024 | COT - HCBU - Building Final | Partial Pass | 12/2/24: exterior receptacles must be WR GFCI, exhaust fan in office bathroom no power, GFCI required at break room outlets, dishwasher must be properly installed/supported, overflow switch required at air handlers, supports at water heater copper pipes must be coated, Bathroom signage must be installed at time of inspection, condenser unit tripped breaker multiple times during inspection. OK FOR LEVEL 2 TCO. 12/13/24: corrections have been made. Pending conditions. |
|
| 12/20/2024 | COT - HCBU - Building Final | Partial Pass | 12/2/24: exterior receptacles must be WR GFCI, exhaust fan in office bathroom no power, GFCI required at break room outlets, dishwasher must be properly installed/supported, overflow switch required at air handlers, supports at water heater copper pipes must be coated, Bathroom signage must be installed at time of inspection, condenser unit tripped breaker multiple times during inspection. OK FOR LEVEL 2 TCO. 12/13/24: corrections have been made. Pending conditions. 12/20/24: ok for level 4 TCO |